CE / FCC / RoHS Compliance Path for Custom Industrial Computers
What a custom industrial PC needs to ship legally in the EU and US: which directives apply, which standards the lab tests, typical timelines and costs, and which documents the manufacturer must keep on file.
Quick answer
For the EU: a custom industrial PC falls under the EMC Directive 2014/30/EU and, with an AC adapter or mains supply, the Low Voltage Directive 2014/35/EU, plus RoHS 2011/65/EU. For the US: FCC Part 15 Subpart B (unintentional radiator, digital device). None of these require a notified body for this product class — the manufacturer tests, assembles the technical file and self-declares. Budget roughly 3–5 weeks and a few thousand dollars for a full custom model, less for a variant of an already-certified platform.
The CE path (EU), step by step
- Identify applicable legislation: EMC + LVD (if mains-connected) + RoHS; machinery directive only if the PC is sold as part of a machine you also supply.
- EMC testing at an accredited lab: emissions to EN 55032 (Class A for industrial environments), immunity to EN 55035 (ESD, EFT, surge, RF fields).
- LVD electrical safety: EN 62368-1 (with mains PSU) — often covered by using a certified external adapter.
- RoHS: gather material declarations from every component supplier; the lab or your team assembles the declaration.
- Technical file + EU Declaration of Conformity (DoC): test reports, BOM declarations, DoC listing standards and signatory. Keep it for 10 years.
- Mark CE on the product and ship. No yearly certificate renewal, but re-test when hardware changes materially.
The FCC path (US)
Digital electronics without radio: FCC Part 15 Subpart B, Class A (industrial/commercial) — verification or Supplier's Declaration of Conformity, tested to ANSI C63.4. If the unit contains Wi-Fi/5G modules, the modules carry their own grants and the host needs additional evaluation. FCC does not require CE-style marking; the compliance statement goes in the manual.
Documents a buyer should ask any manufacturer for
- CE Declaration of Conformity (naming the exact standards and versions)
- EMC test reports from the lab (with the tested configuration)
- RoHS declaration and supplier material declarations
- FCC compliance statement / test report
Cost and time reference (custom model)
| Item | Typical range | Time |
|---|---|---|
| EMC emissions + immunity | USD 2,000–5,000 | 1–2 weeks lab time |
| LVD safety (if needed) | USD 1,500–4,000 | 1–2 weeks |
| FCC Part 15B | USD 1,000–3,000 | 1 week |
| RoHS compilation | Often bundled | Days, depends on BOM discipline |
Platform reuse is the biggest cost lever: a customized variant that keeps the certified PCB/platform layout inherits most of the test evidence and needs only delta testing.
Frequently Asked Questions
Does CE certification for an industrial PC require a notified body?
No. Industrial PCs are self-declarable: the manufacturer tests against harmonized standards (EN 55032, EN 55035, EN 62368-1), assembles the technical file and signs the EU Declaration of Conformity. A notified body is only needed for special cases outside the normal directives.
How long does CE + FCC testing take for a custom industrial computer?
Typically 3 to 5 weeks end to end for a new model: lab scheduling, one to two weeks of testing across EMC (and safety if mains-powered), plus report and declaration preparation. Variants of an already-certified platform often need only delta testing.
Do I need new CE testing if I only change the CPU or add a card?
Minor changes on the same certified platform usually require only a documented assessment and possibly delta EMC testing; a material hardware change (new board, new PSU, new enclosure) means re-testing. Ask the manufacturer how the change affects the technical file — a competent one will answer specifically.